Update #3: August 4, 2015 Remaining Work: – Construction of¬† 2 tap stands, – Protection of pipes and a part of connection pipes Update #2: July 16, 2015 – 2 sources catchment protection are completed – Construction¬† Tank 1 is completed – Construction tank 2 is on 30% completion, – 5 tap stand are completed – Digging trenches is around 3.5km -Connection¬† of pipes is around 2.3km   Update #1: May 26, 2015 A signed contract has been returned by the project manager and construction will begin soon! Expected length of work on system is generally 12-15 weeks but due to the ongoing political conflict could be delayed. Project Details The Songa Commune of the Bururi Provence in Burundi has very limited clean water resources. Currently the local inhabitants walk significant distances to obtain water from small springs and water pools that are not clean. The project will consist of one 0.3 liter-per-second source and collection chamber and connect to one five-cubic-meter tank and one ten-cubic-meter tank. Eight tap stands will be distributed over 4.0 kilometers of pipeline. The tap stands (fountains) will provide access to the clean water source. Throughout the entire project, the pipeline will be buried below ground. Tap stands will include appropriate drainage. The project will serve approximately 1,000 people from the surrounding population. [fbalbum url=https://www.facebook.com/media/set/?set=a.10153110394097946.1073741843.151186542945&type=3] To view history on all Gazelle Foundation water systems, visit HERE. Drawing of Gihoro-Sama water system.docx